ID Unique ID
Task Name
Duration Type Outline Level Baseline Duration Predecessors Start Date Finish Date Early Start Early Finish Late Start Late Finish Free Slack Total Slack Leveling Delay Percent Complete Actual Start Actual Finish Baseline Start Baseline Finish Constraint Type Constraint Date Stop Resume Created Scheduled Work Baseline Work Actual Work Cost Fixed Cost Baseline Cost Actual Cost Remaining Cost WBS Priority Milestone Summary Rollup Text1 Text2 Text3 Text4 Text5 Text6 Text7 Text8 Text9 Text10 Cost1 Cost2 Cost3 Duration1 Duration2 Duration3 Flag1 Flag2 Flag3 Flag4 Flag5 Flag6 Flag7 Flag8 Flag9 Flag10 Marked Number1 Number2 Number3 Number4 Number5 Subproject File
1 1
Project Kick-Off
6 days Fixed Duration 1 0 days?   Jan 3 Jan 10 Jan 3 Jan 10 Jan 3 Jan 11 0 days 0 days 0 edays 0% NA NA NA NA As Soon As Possible NA NA NA Feb 22 368 hrs 0 hrs 0 hrs $0.00 $0.00 $0.00 $0.00 $0.00 1 500 No Yes Yes                     $0.00 $0.00 $0.00 0 days 0 days 0 days No No No No No No No No No No No 0 0 0 0 0